Glossary > —C— > Complete before Summarization
Complete before Summarization
A multi-period calculation setting for a scenario on the Scenarios page. Yes is displayed in this column for the scenario on the Scenarios page when this option is selected for the scenario.
When selected, the scenario calculation process is treated as two separate tasks; Calculate Stocking Levels and Calculate Summary Levels. This enables the visibility of the data as follows:
Calculate Scenario Step
After Completion
Calculate Stock Levels
1. You can view the output of the stock level calculations on these pages:
SKU Summary
SKU Detail Report
Inventory Collaboration
Part Supply Chain
2. You can run these AutoPilot processes:
Make Production
Generate Order Plan
3. The summary calculation for each interval begins processing in the background.
Calculate Summary Values
The summary values are updated on these pages after all intervals are summarized:
Scenario Summary
Part Summary
Location Summary
Segment Summary
Service Group Results
When this option is not selected, the stock level calculations and the interval summary calculations must all be completed before the data is visible on any page. No additional processing can begin until both steps of the calculation process complete.